Local Plan Timetable

The government has introduced a new 30-month timescale in which we have to produce the District Local Plan. 

Before this 30-month period commences we also have to give at least 4 months notice of our intention to start preparing the Local Plan Plan and publish our timetable. The timetable includes 3 Gateway Assessments with government to check our progress.

Our timetable for preparing the Local Plan is published below, in accordance with Regulation 4 of the Town and Country Planning (Local Planning) (England) Regulations 2026. 

This timetable was first published and effective 06 July 2026 and the draft amended timetable published October 2026. It includes the key milestone dates for the end-to-end process for preparing the Local Plan.

The Draft timetable and scoping consultation is subject to approval at Cabinet on 08 October 2026 and Full Council on 22 October 2026.

Local Plan Stages

 

Get Ready

 

06 July 2026

Notice of intention to commence plan preparation available

14 January 2027

28 February 2027

The scoping consultation will start and end

01 March 2027

The Gateway 1 self-assessment summary will be published

Prepare the Plan

 

28 July 2027

08 September 2027

The consultation on proposed plan content and evidence will start and end.

11 January 2028

Observations and advice will be sought for Gateway 2

22 May 2028

17 July 2028

The consultation on the proposed plan will start and end

02 November 2028

Observations and advice will be sought for Gateway 3

Examination and Adoption

 

02 January 2029

Plan submitted for examination

01 September 2029

Adopt the plan

 

Forest of Dean District Design Guide – Supplementary Plans Timetable

This is the timetable was first published and effective from 06 July 2026, the draft amended timetable was published October 2026. It includes the key milestone dates for the end-to-end process for preparing a Supplementary Plan.

Dates Supplementary Plan Stages

06 July 2026

Notice of intention to commence supplementary plan preparation

02 May 2028

Consultation on the proposed supplementary plan will start.

17 July 2028

Consultation on the proposed supplementary plan will end

30 September 2028

Supplementary plan submitted for examination

31 January 2029

Adopt the supplementary plan

 

Forest of Dean District Landscape Study – Supplementary Plans Timetable

This is the timetable was first published and effective from 06 July 2026, The draft timetable was published October 2026. It includes the key milestone dates for the end-to-end process for preparing a Supplementary Plan.

Dates Supplementary Plan Stages

06 July 2026

Notice of intention to commence supplementary plan preparation

28 July 2027

Consultation on the proposed supplementary plan will start.

08 September 2027

Consultation on the proposed supplementary plan will end

30 October 2027

Supplementary plan submitted for examination

01 February 2028

Adopt the supplementary plan

 

Download a csv version of the Local plan timetable.

This CSV file contains the information in the timetable above and will be updated when changes have been made to the timetable and when milestones have been met. The data within this file is being provided to government under the Open Government Licence.

Timetable changes

The timetable will be reviewed monthly from the date of publication and updated when any changes are required.

We will also update timetable on the same day that the following stages are reached:

  • publication of Gateway 1 self-assessment
  • publication of Gateway 2 advice
  • publication of Gateway 3 advice
  • publication of the recommendations and reasons of the examiner following the examination of the plan

Local plan timetable schedule of amendments

  • 06 July 2026: First version of Local Plan Timetable published.
  • 1 October 2026: Last review of the Timetable.
    Draft Local Plan Timetable updated with revised milestone dates to be agreed at Full Council 22 October 2026.
  • 06 November  2026 Next scheduled review of the Timetable: